Installation recommendations

Floating dry floor screed

on wooden beam floor with existing planking

1. 22/25 mm flooring panel or cement fibreboard

2. 2.5 mm MEHARIPP or 8/10 mm MEHASOL

3. Approx. 10-80 mm MEHABIT

4. MEHAFIPP as trickle protection (if necessary)

5. Existing wooden floor boards

6. Wooden beam floor with heavy filling (loam, cinder)

Floating dry floor screed

on wooden beam floor with heavy filling

1. 22/25 mm flooring panel or cement fibreboard

2. Sound insulating mat (optional)

3. 8/10 mm MEHASOL load distribution plate

4. Approx. 10-80 mm MEHABIT

5. Wooden beam floor with heavy filling (loam, cinder)

Dry floor screed

on uneven concrete surface (full-area processing of fill)

1. 22/25 mm flooring panel or cement fibreboard

2. 2.5 mm MEHARIPP or 8/10 mm MEHASOL

3. Approx. 10-80 mm MEHABIT for compensating unevenness and for covering cable bundles

4. 150 mm solid layer with moisture barrier